    EQUIPMENT DETAILS Water Booster pump

    SCHEDULE OF PLANNED PREVENTIVE MAINTENANCE Work Plan


    [​IMG]

    EQUIPMENT DETAILS Water Booster pump

    صيانة دورية جداول جاهزة نظام مضخة زيادة ضغط الماء

    Capacity
    Qty: Lot
    Make & Model

    Location

    Smoke Fan

    Water Booster pump

    Task Description
    W / Weekly M / Monthly Q / Quarterly SA/ Semi/Annually
    A/ Annually SST / Seasonal Start/Up SSH / Season Shut Down
    2W M 3M
    6M A Notes

    Item Description
    Qty Notes

    Critical Tasks
    Operate manually all pumps
    Examine water and air pressure gauge
    Check all valves for free travel
    Test audible alarm
    Check glands for leaks if necessary tighten
    Inspect unit for unusual noise and/or vibration, ensure that it is in good working order.
    Provide lubrication, if necessary.
    If unit is not running or an identified problem requires the unit to be serviced, perform ALL Non-
    Critical Tasks listed below.

    Flush and clean strainers.
    Check operation of gauges and record pressures and temperatures.
    Inspect seals and packing, tighten or replace as necessary.
    Lubricate impeller shaft bearings.
    Inspect motor and pump alignment.
    Other recommended tasks
    Inspect mounting bolts and vibration isolators of the pump under load conditions.
    Start and stop pump, noting any vibration and overall performance.
    Inspect drive shaft coupling.
    Operate manually all pumps

    Check all valves for free travel
    Examine water and air pressure gauge
    Test audible alarm
    Check glands for leaks if necessary tighten
    Clean all strainers
    Examine pipe work & connection for leak
    Lubricate all bearings
    Blowout all dust from control panel, pump and
    motor
    Check alignment ( coupling )
    Check all operating control if necessary adjust
    Check for necessary paint


    Notes
    Use additional sheets if required
    PPM routines based on Complete
    Running hour where recommended by the Manufacturer


    [​IMG]