    EQUIPMENT DETAILS Chillers Annual PREVENTIVE MAINTENANCE


    SCHEDULE OF PLANNED PREVENTIVE MAINTENANCE Work Plan


    SCHEDULES OF PLANNED PREVENTATIVE MAINTENANCE Work Plan


    [​IMG]

    EQUIPMENT DETAILS Chillers Annual PREVENTIVE MAINTENANCE

    صيانة دورية جداول جاهزة نظام بوابات الدخول المؤمنة

    جاهزة للتحميل و سهلة التعديل و الطباعة مايكروسوفت وورد ملفات

    EASY AND READY TO BE DOWNLOADED , MODIFIED AND PRINTED

    MICROSOFT WORD DOCUMENTS TECHNICAL DATA SCHEDULES

    Capacity
    Qty: Lot
    Make & Model

    Location
    Chillers Annual PREVENTIVE MAINTENANCE


    Task Description
    W / Weekly M / Monthly Q / Quarterly SA/ Semi/Annually
    A/ Annually SST / Seasonal Start/Up SSH / Season Shut Down
    2W M 3M
    6M A Notes

    Item Description
    Qty Notes

    Critical Tasks to be performed

    Change oil filter, refrigerant dryer filter element, oil cooler filter element
    Change of oil in the gearboxes – if applicable
    Check compressor oil
    Remove end covers from evaporators and condensers, wire Bruch and/or chemically clean all scales from tubes. Clean and scrape end covers and doors, paint with suitable anti-corrosive paint

    Renew zinc anodes as required if applicable
    Renew gaskets, re-assemble, check and make leak test
    Inspect, test, calibrate & repair or replace as necessary: all main and off-season plant controls, cut-outs, safety devices, pneumatic control system, pressure, temperature and level indicating and recording instruments, voltage, current indicating instruments
    Inspect, test and repair or replace as necessary: all electrical Motors, starters, overloads etc..
    Check and tighten or replace any vibration isolators
    Clean and paint all equipment

    Other recommended tasks

    Leak test of chiller
    Check Pump down Unit
    Clean: float chamber, orifice and strainer
    Inspection by manufacturer’s representatives
    Major overhauls to be carried out to Main and off-season air conditioning plants and ancillary equipment seasonally


    Notes
    Use additional sheets if required
    PPM routines based on Complete
    Running hour where recommended by the Manufacturer